Flood Remediation Project – Watercourse 11 Fifty Point Conservation Area Notice of Public Information Centre No. 2

Loading Map....

Date/Time
Date(s) - Wed. Jun 13, 2018
6:00 pm - 8:00 pm

Location
Fifty Point Conservation Area

Categories


Flood Remediation Project – Watercourse 11

Fifty Point Conservation Area Notice of Public Information Centre No. 2


THE STUDY
The Hamilton Conservation Authority (HCA) has commenced a study to investigate possible flood remediation measures for Watercourse 11 in Fifty Point Conservation Area including the private lands and City of Hamilton lands located to the north. The privately held lands contain residential dwellings that may be impacted by this flooding. The focus of this study is to investigate the causes of the flooding and provide an evaluation of alternative solutions to the flooding issue, as well as finalize the preliminary design for the preferred alternative for flood remediation, if applicable. The study area is shown on the attached map.


THE PROCESS
The study is being conducted in accordance with Conservation Ontario’s procedures as outlined in the Class Environmental Assessment(EA) for Remedial Flood and Erosion Control Projects (2002, amended June 2013). The Project Team, at the PIC # 2, will present the study progress to date and the preliminary recommended alternatives. Attendees will have the opportunity to meet with the Team and review the alternatives and their evaluation to address flooding in the study area.


PUBLIC CONSULTATION
Please join us at our second Public Information Centre (PIC #2) to learn more about the study, existing conditions in the study area, preliminary recommended alternatives, and the next steps in the study process. The Public Information Centre will be a drop-in open house that will provide an opportunity for you to view display boards, discuss the project with the HCA staff, consultant staff, and provide input into the planning process. Details are as follows:

DATE: June 13, 2018
TIME: 6:00 p.m. to 8:00 p.m.
LOCATION: Fifty Point Conservation Area – Marina Office (Located Under Limani Restaurant), 1479 Baseline Road, Stoney Creek, Ontario


Comments and information regarding the study will be collected to assist the HCA in meeting the requirements of the Class EA process. If you wish to be involved in this study, provide comments, ask questions, or receive information, please contact one of the project representatives identified below. Additional information on the project, as well as additional consultation opportunities will be made available as the study progresses.

Hamilton Conservation Authority
Mr. Scott Peck, MCIP, RPP
Deputy Chief Administrative Officer/ Director, Watershed Planning & Engineering
838 Mineral Springs Road
Ancaster, ON L9G4X1
Phone: 905.525.2181 ext.130
Email: tspeck@conservationhamilton.ca

AHYDTECH Geomorphic Ltd.
Dr Bahar SM, P.Geo.(Ltd), P.Eng.
Managing Director, Lead Manager